by RISE Communications | Apr 20, 2016 | Construction, YUCWMENLÚCWU
Landmark and YUCWMENLÚCWU partnered to remove a load restricted bridge and replace with a steel girder bridge with timber deck panels. The process involved temporary positioning of the bridge to provide equipment access during construction of the geosynthetic...
by RISE Communications | Apr 20, 2016 | Construction
In 2013, Columbia Power Corporation (CPC) on behalf of BC Hydro contracted SCES to remove the deteriorating timber/pile supported boat ramp at Nakusp BC (Arrow Lake) and replace it with a concrete launch. The new concrete ramp is comprised of a combination of...
by RISE Communications | Apr 20, 2016 | Construction
The District of Sicamous contracted SCS to construct a public boat launch in Old Town Bay in preparation for the 2016 boating season. The project involved precast concrete panels and concrete planks to transition from shore to the lakebed. The project, completed in...
by RISE Communications | Mar 19, 2016 | Construction
SCS was contracted to construct a pile-supported platform, ramp and dock to improve access to this important recreation area. Owner – City of Enderby (2016) Book a...
by RISE Communications | Jun 20, 2015 | Construction
SCS was contracted by BC Hydro to continue extensive modifications to river bank protection (rip rap) adjacent to the Revelstoke Golf Course. Building on the work initiated in 2009, the slope preparation and placement of an additional 4700 m3 of rip rap over 1300...